1 :MW03B
2: MW14A
3:MW08A
4: MW13B






1 :MW03B
2: MW14A
3:MW08A
4: MW13B






Installation and Commissioning of the vacuum circuit breaker is relatively simple, and it is a process that must be completed before leaving the…
Finding: MOV 2V07-L opening & closing time percentage isn’t showing properly in SCADA & Field side. Action Taken: Reset the MOV-2V07.
Problem: Do not show footage in NAV.Problem found: POE Switch problem & 1 nos cc camera damage found and New POE Switch installing. Now problem…
Problem: SCADA always showing HI signal. Problem found: 1 NOS float switch problem found. A good sensor in HIHI position is replaced with…
PIT maintenance work reportDtw-213 maintenance. Now okDtw-208 maintenanceNow okDtw-207 maintenanceNow okDtw-211 PIT damagedDtw-203 PIT doesn’t exist.Dtw-205 PIT damagedDtw-206 SCADA PACK doesn’t exist
One Comment