1 :MW03B
2: MW14A
3:MW08A
4: MW13B






1 :MW03B
2: MW14A
3:MW08A
4: MW13B






1.Cable connector change 2. IP Setup
DTW-102 Scada Pack Programing And Install Done
IRP-1 All LOP Panel Cleaning Done
IRP- 2 1nos CC Camera Maintenance done, there was connector problem. now IRP-2 Sub-Station all CC Camera in operation.