IRP-1 All LOP Panel Cleaning Done
26.11.2023 Today SEL manpower change the e-PRV CRD spring. And we check the e-PRV functionality is okay or not okay. MOV-1 50% Open,…
1.CCTV Pool Installation 2.CCTV Camera Cage Installation 3.UTP Cable Installation
Observation: DTW 107 Radio Communication checking complete. This DTWs communication is very bad.1. In DTW 107, We checked up to 10 minutes. In…