| Employee Name | Faysal Zaman | Job Title | Electrician | 
| Supervisor/Reviewer | MD Zahid Hossain | Month | Jun – July 2022 | 
Task List
| SL. NO | Work Name | Estimated Completion Date | Completion Date | Comments | Report | 
| 01. | Monthly Report Submission | 18/07/2022 | 16/07/2022 | Activity Report | |
| 02. | CCTV Camera Checking, Cleaning and frontside tree trimming (23 Nos) | 26/07/2022 | |||
| 03. | POE Switch Checking and Cleaning (23 Nos) IRP-1 | 26/07/2022 | Activity Report | ||
| 04. | ONU Checking and Cleaning (23 Nos) | 26/07/2022 | Activity Report | ||
| 05. | CCTV Camera servicing (23 Nos) | 26/07/2022 | Activity Report | ||
| 06. | CCTV UPS Checking and Cleaning (23 Nos) | 26/07/2022 | Activity Report | ||
| 07. | IRP-1 CCTV Server Panel Checking and Cleaning | 15/07/2022 | |||
| 08. | IRP-2 CCTV OLT Server Panel Checking and Cleaning | 15/07/2022 | Activity Report | ||
| 09. | IRP-1 SCADA Room Printer Checking and Cleaning | 20/07/2022 | Activity Report | ||
| 10. | IRP-1 SCADA Room RTU and Server panel cleaning | 08/07/2022 | Activity Report | ||
| 11. | IRP-2 SCADA Room RTU and Server panel cleaning | 12/07/2022 | Activity Report | ||
| 12. | IRP-1 Electrical Room RTU panel cleaning | 22/07/2022 | Activity Report | ||
| 13. | IRP-1 OGR Electrical Room RTU panel cleaning | 24/07/2022 | Activity Report | ||
| 14. | IRP-1 Dome Camera Checking and Frontside Cleaning | 23/07/2022 | Activity Report | ||
| 15. | IRP-1 Dome Camera Panel Checking and Cleaning | 23/07/2022 | Activity Report | ||
| 16. | IRP-2 Dome Camera Checking and Frontside Cleaning | 24/07/2022 | Activity Report | ||
| 17. | IRP-2 Dome Camera Panel Checking and Cleaning | 24/07/2022 | Activity Report | ||
| 18. | Fiber Optic Cable Checking and Reporting | 26/07/2022 | Activity Report | ||

 
			 
			