In the time of Civil work the contractor’s people cuts down the fiber cable to conduct their civil work. As a result this DTW was out of our security system.
Similar Posts
CCTV Maintenance At DTW-209
Posted on
1.Cable connector change 2. IP Setup
CCTV Maintenance At DTW-219
Posted on
1 new camera installation 2. UTP cable change 3. Connector change 4. IP Setting 5. IP Seating
ACTIVITY | DAILY REPORTS | DTW
DTW-113 Scada Pack Install
Posted on
DTW-113 Scada Pack Programing And Install Done
DTW115 SCADA PACK INSTALL COMPLETE
Posted on
ACTIVITY | DAILY REPORTS | Parvez | REPORTS
OGR Booster room dewatering pump run command showing problem at low level
Posted on
Float switch reconnection and rearrange. Now normal
One Comment