Daily Work Plan October 2022🠗 SL/NO Date PROBLEMS TYPE LOCATION REMARK 1 01.10.2022 DTW-105 CCTV checking maintenance. COR CCTV Team ICE: ✅PAPPU, Parvez,…
The modbus serial communication cable is cut by mouse. The cable reconnect & solve the problem.
DTW-212 & 222 CCTV Maintenance Done Connector Change Now DTW-212 & 222 10 No’s CCTV Operation in NAV
There is so much dust so we Plant grass to prevent road side dust
Problem: Do not show footage in NAV.Problem found: ONU & 1 Nos cc camera Problem found.
CCTV modification work for Dual power source Done Now CCTV continuous View remain All time.