ACTIVITY | DTW | MONTHLY REPORTS | Pappu DTW-208 RTU PANEL, VFD CLEANING & CHECKING COMPLETE. Posted onSeptember 6, 2022September 6, 2022
ACTIVITY | DAILY REPORTS | DTW | Pappu DTW-122 PIT Fuse and Serial communication cable check and maintenance complete. Posted onOctober 24, 2022October 24, 2022 DTW-122 PIT Fuse and Serial communication cable check and maintenance complete.Problem: PIT value not showing in the SCADA.Problem found: 1. PIT 24v DC…
ACTIVITY | DAILY REPORTS | Jewel | Parvez | REPORTS IRP-2 Sub-Station Re cleaning Posted onDecember 13, 2022December 13, 2022 There was so much dust
ACTIVITY PWID16:DTW116 Bullet camera glass and cage cleaning. Posted onNovember 16, 2023November 16, 2023
ACTIVITY | REPORTS Scada Related Problem ( PIT Interlock ) Posted onOctober 12, 2022December 11, 2022 PIT Interlock