Checking and maintenance of 2 field pumps completed.





Checking and maintenance of 2 field pumps completed.
IRP-1 SDB Additional Dewatering Pump check: 1. Motor winding Resistance check (Normal) 2. Motor Ampere check (Normal) 3. MC coil check ( little…
Problem found: POE Switch & 4 NOS CC camera problem found.
IRP- 2 1nos CC Camera Maintenance done, there was connector problem. now IRP-2 Sub-Station all CC Camera in operation.