IRP#01 Main substation, Electrical Panel Room, OGR Electrical Panel Room Cleaning & Visual Check Work Completed.



IRP#01 Main substation, Electrical Panel Room, OGR Electrical Panel Room Cleaning & Visual Check Work Completed.
1.1 Nos New Camera Installation . 2. connector change 3. IP Setup
DTW-122 PIT Fuse and Serial communication cable check and maintenance complete.Problem: PIT value not showing in the SCADA.Problem found: 1. PIT 24v DC…
There was a damaged LIT. After regeneration work we have install a new LIT
1.Cable connector change 2. IP Setup