IRP#01 Main substation, Electrical Panel Room, OGR Electrical Panel Room Cleaning & Visual Check Work Completed.
Similar Posts
ACTIVITY | DAILY REPORTS | Jewel | REPORTS
IRP-1 All LOP Panel Cleaning
Posted on
IRP-1 All LOP Panel Cleaning Done
DTW-201 CCTV checking
Posted on
Problem: Do not show footage in NAV.Problem found: ONU & 1 Nos cc camera Problem found.
DTW -118 Radio Communication checking complete.
Posted on
Observation: DTW 118 Radio Communication checking complete. This DTWs communication is very bad.1. In DTW 118, We checked up to 10 minutes. RSSI…
ACTIVITY | DAILY REPORTS | Pappu | REPORTS
IRP-2 ALL LOP Panel Cleaning
Posted on
There was so much dust
A new ONU install at DTW-201.
Posted on
Previous ONU frequently becomes unstable/hang. So replace the ONU.