Similar Posts
DTW-113 LIT,PIT,FIT isolation due to regeneration
Posted on
Unable to take LIT, due to keep heavy machinery in DTW compound. We collect Electronic PIT, Manual Pressure Gauge. And disconnect power supply…
ACTIVITY | CCTV | DAILY REPORTS | DTW | Parvez
DTW-122 & 123 Optical Fiber Maintenance
Posted on
DTW-122,123 optical fiber maintenance: We check TJ box in both dtw. Optical fiber checked by Leaser Light. Leaser light throw from dtw-122 to…
DTW-104,105,106,107 CLEANING WORK
Posted on
DTW-104,105,106,107 Cleaning Done
IRP-2 Server Rak Installation
Posted on
IRP-2 Sub-Station 1Nos New Server Rack Installation Done
ACTIVITY | DAILY REPORTS | Jewel | Pappu | Parvez
4 nos Monitoring Well Level Sensor Installation Complete.
Posted on
1 :MW03B 2: MW14A 3:MW08A 4: MW13B
Optical Fiber Maintenance
Posted on
Due To Strom the optical fiber cable fall down and damage near DTW-209 to 206 Now Everything is Normal