ACTIVITY PWID26:DTW203 Bullet camera glass and cage cleaning. Posted onNovember 16, 2023November 16, 2023
ACTIVITY | DTW | MONTHLY REPORTS | Pappu DTW-208 RTU PANEL, VFD CLEANING & CHECKING COMPLETE. Posted onSeptember 6, 2022September 6, 2022
ACTIVITY | DAILY REPORTS | DTW | Pappu | REPORTS IRP-1 (101 to 123) & IRP-2 (201 to 223) I & C device checking complete. Posted onOctober 22, 2022October 22, 2022
ACTIVITY | DAILY REPORTS | DTW | Jewel | Pappu | Parvez | REPORTS IRP-2 Server Rak Installation Posted onNovember 16, 2022November 16, 2022 IRP-2 Sub-Station 1Nos New Server Rack Installation Done
ACTIVITY | CCTV | OFFICIAL NOTE | Uncategorized Fiber Optical Maintenance Posted onOctober 23, 2022October 23, 2022 Fiber Optical Maintenance Near DTW-103
ACTIVITY | DAILY REPORTS | DTW | Pappu DTW 117 PIT Checking and maintenance complete. Posted onOctober 10, 2022October 10, 2022 Problem: PIT value does not showing in the SCADA & field device.Problem found: PIT 24v AC supply fuse damage found & maintenance. now…