ACTIVITY PWID51:DTW210 to 222 TJ Box sealing with silicon glue. Posted onNovember 25, 2023November 25, 2023
ACTIVITY | DAILY REPORTS | DTW | Jewel | Parvez PIT Maintenance Work Report (IRP-1) Posted onNovember 9, 2022November 9, 2022 DTW-114 PIT ok. DTW-113 PIT ok but scadapack AO port damaged. DTW-104 PIT doesn’t exist. DTW-105 PIT ok (regeneration on going)
ACTIVITY PWID54,DTW107,109,110,111,112 111 RTU & CCTV Panel Clening Posted onNovember 28, 2023November 29, 2023
ACTIVITY | CCTV | DAILY REPORTS | DTW | Jewel | Pappu | Parvez DTW-206 New POE Switch installing & CC Camera checking Posted onSeptember 12, 2022September 12, 2022 Problem found: POE Switch & 4 NOS CC camera problem found.
ACTIVITY PWID10:DTW110 Bullet camera glass and cage cleaning. Posted onNovember 16, 2023November 16, 2023
ACTIVITY | CCTV | DTW | Jewel | MONTHLY REPORTS CCTV PANEL, UPS, POE SWITCH, ONU CLEANING COMPLETE DTW-203 . Posted onSeptember 5, 2022September 6, 2022