  • ACTIVITY | DAILY REPORTS | DTW | Pappu | REPORTS

    DTW- 120 LIT And PIT Maintenance

    Posted onNovember 14, 2022November 14, 2022

    DTW-120 PIT maintenance Done. Rearrange cable waring. fuse change.now PIT is ok and give proper value in scada LIT Do Not Down in…

    Listen to the Message DTW- 120 LIT And PIT MaintenanceContinue

  • ACTIVITY | DAILY REPORTS | DTW | Jewel | Parvez | REPORTS

    OPTICAL FIBER MAINTENANCE AT DTW-104

    Posted onNovember 14, 2022November 14, 2022

    In DTW-104, the optical fiber is broken by lizard in TJ box. We rejoin the optical fiber. Now CCTV can be seen in…

    Listen to the Message OPTICAL FIBER MAINTENANCE AT DTW-104Continue

  • ACTIVITY | DAILY REPORTS | DTW | Jewel | Parvez | REPORTS

    DTW-202 NEW LIT INSTALLATION

    Posted onNovember 14, 2022November 14, 2022

    There was a damaged LIT. After regeneration work we have install a new LIT

    Listen to the Message DTW-202 NEW LIT INSTALLATIONContinue

  • IRP-1 DTW RTU,VFD & CCTV Panel Cleaning
    ACTIVITY | DAILY REPORTS | DTW | Jewel | Pappu | Parvez | REPORTS

    IRP-1 DTW RTU,VFD & CCTV Panel Cleaning

    Posted onNovember 13, 2022November 15, 2022

    Dtw 101,102,103,109,110 RTU panel , VFD internal site & CCTV panel cleaning complete .

    Listen to the Message IRP-1 DTW RTU,VFD & CCTV Panel CleaningContinue

  • DTW- 221 VFD And LIT Installation
    ACTIVITY | DAILY REPORTS | DTW | Jewel | Parvez | REPORTS

    DTW- 221 VFD And LIT Installation

    Posted onNovember 12, 2022November 12, 2022

    Modbus Serial communication cable check Complete. No problem Found in the Field LIT Do Not Down in The Boring After 10 Meter

    Listen to the Message DTW- 221 VFD And LIT InstallationContinue

  • IRP-2 RTU & VFD Panel Cleaning
    ACTIVITY | DAILY REPORTS | DTW | Pappu | REPORTS

    IRP-2 RTU & VFD Panel Cleaning

    Posted onNovember 12, 2022November 12, 2022

    IRP-2 RTU Panel, Server Panel & VFD Panel Cleaning Done

    Listen to the Message IRP-2 RTU & VFD Panel CleaningContinue

  • PIT Installation
    ACTIVITY | DAILY REPORTS | DTW | Jewel | Parvez | REPORTS

    PIT Installation

    Posted onNovember 11, 2022November 11, 2022

    DTW-205 1Nos New PIT Installation Done DTW-211 1Nos New PIT Installation Done DTW-104 1Nos Old PIT Installation Done

    Listen to the Message PIT InstallationContinue

  • FIT Maintenance Work Report (IRP-2)
    ACTIVITY | DAILY REPORTS | DTW | Pappu | REPORTS

    FIT Maintenance Work Report (IRP-2)

    Posted onNovember 11, 2022November 13, 2022

    প্ল্যান্ট শুরুর পর হতে অদ্যাবধি ফ্লো-মিটারের মেইন্টেনেন্স কাজ করা হয়নি। মেক্যানিক্যাল ফ্লো-মিটার হওয়ার কারনে যদি ও ঠিকমত রিডিং পাওয়া যায়না, তদুপরি প্রাপ্ত পালসের…

    Listen to the Message FIT Maintenance Work Report (IRP-2)Continue

  • DTW- 208 Fault Come in CCTV UPS
    ACTIVITY | CCTV | DAILY REPORTS | DTW | Jewel | Parvez | REPORTS

    DTW- 208 Fault Come in CCTV UPS

    Posted onNovember 9, 2022November 9, 2022

    Dtw-208 CCTV power supply is received from directly LV panel. Frequently Fault come in UPS. Now Everything is Normal.

    Listen to the Message DTW- 208 Fault Come in CCTV UPSContinue

  • FIT Maintenance Work Report  (IRP-1)
    ACTIVITY | DAILY REPORTS | DTW | Pappu | REPORTS

    FIT Maintenance Work Report (IRP-1)

    Posted onNovember 9, 2022November 13, 2022

    প্ল্যান্ট শুরুর পর হতে অদ্যাবধি ফ্লো-মিটারের মেইন্টেনেন্স কাজ করা হয়নি। মেক্যানিক্যাল ফ্লো-মিটার হওয়ার কারনে যদি ও ঠিকমত রিডিং পাওয়া যায়না, তদুপরি প্রাপ্ত পালসের…

    Listen to the Message FIT Maintenance Work Report (IRP-1)Continue

Page navigation

Previous PagePrevious 1 … 10 11 12 13 14 … 26 Next PageNext

Dhaka Water Supply and Sewerage Authority

+88 01797187749

Join With Us

© 2025 TEAM ICE

  • Home
  • ICE LAB
  • Product Specifications
  • Technical Papers