    ACTIVITY | DTW | DTW103 | Parvez

    DTW-103 VFD Controller Install

    Posted onNovember 3, 2022November 3, 2022

    1.DTW-103 New VFD Controller Install 2. Parameter set 3.Serial Communication Cable Wiring Work Done

    Listen to the Message DTW-103 VFD Controller InstallContinue

  • CCTV Maintenance At DTW-103
    ACTIVITY | CCTV | DTW | DTW103

    CCTV Maintenance At DTW-103

    Posted onOctober 27, 2022October 27, 2022

    CCTV Pool adjustments 1 new camera installation 1 new PoE Switch installation UTP cable change IP Setting

    Listen to the Message CCTV Maintenance At DTW-103Continue

  • EPRV Work DTW-117 By ICE Team & SEL
    ACTIVITY | DTW | DTW103

    EPRV Work DTW-117 By ICE Team & SEL

    Posted onOctober 22, 2022October 22, 2022

    DTW-117

    Listen to the Message EPRV Work DTW-117 By ICE Team & SELContinue

  • Optical Fiber restoration work at DTW103
    ACTIVITY | CCTV | DTW103 | Jewel | NETWORK CONNECTIVITY | Pappu | Parvez

    Optical Fiber restoration work at DTW103

    Posted onSeptember 7, 2022September 24, 2022

    In the time of Civil work the contractor’s people cuts down the fiber cable to conduct their civil work. As a result this…

    Listen to the Message Optical Fiber restoration work at DTW103Continue

Dhaka Water Supply and Sewerage Authority

+88 01797187749

Join With Us

© 2025 TEAM ICE

  • Home
  • ICE LAB
  • Product Specifications
  • Technical Papers