Skip to content
TEAM ICE
  • Home
  • ICE LAB
  • Product Specifications
  • Technical Papers
TEAM ICE
  • ACTIVITY | DAILY REPORTS | REPORTS

    PIT Report 2022

    Posted onOctober 24, 2022December 11, 2022

    PIT Status October 2022 SL NO. DTW Field Value SCADA Value Remarks 01 101 2.6.kg ✅ OK 02 102 2.1.kg ✅ OK 03…

    Listen to the Message PIT Report 2022Continue

  • DTW-122 PIT Fuse and Serial communication cable check and maintenance complete.
    ACTIVITY | DAILY REPORTS | DTW | Pappu

    DTW-122 PIT Fuse and Serial communication cable check and maintenance complete.

    Posted onOctober 24, 2022October 24, 2022

    DTW-122 PIT Fuse and Serial communication cable check and maintenance complete.Problem: PIT value not showing in the SCADA.Problem found: 1. PIT 24v DC…

    Listen to the Message DTW-122 PIT Fuse and Serial communication cable check and maintenance complete.Continue

  • CCTV Maintenance At DTW-101
    ACTIVITY | CCTV | DAILY REPORTS | DTW | REPORTS

    CCTV Maintenance At DTW-101

    Posted onOctober 23, 2022December 11, 2022

    1.1Nos New Camera Installation 2. UTP Cable Change 3. Connector Change 4. IP setup

    Listen to the Message CCTV Maintenance At DTW-101Continue

  • EPRV work with DTW 103 by ICE Team & SEL
    ACTIVITY | DAILY REPORTS | DTW | Jewel | Pappu | Parvez

    EPRV work with DTW 103 by ICE Team & SEL

    Posted onOctober 22, 2022October 22, 2022

    Listen to the Message EPRV work with DTW 103 by ICE Team & SELContinue

  • IRP-1 (101 to 123) & IRP-2 (201 to 223)  I & C device checking complete.
    ACTIVITY | DAILY REPORTS | DTW | Pappu | REPORTS

    IRP-1 (101 to 123) & IRP-2 (201 to 223) I & C device checking complete.

    Posted onOctober 22, 2022October 22, 2022

    Listen to the Message IRP-1 (101 to 123) & IRP-2 (201 to 223) I & C device checking complete.Continue

  • DTW-111,113,114,115,117,118,119,120,121,122,123    I & C device checking complete.
    ACTIVITY | DAILY REPORTS | DTW | Pappu | REPORTS

    DTW-111,113,114,115,117,118,119,120,121,122,123 I & C device checking complete.

    Posted onOctober 18, 2022October 18, 2022

    Listen to the Message DTW-111,113,114,115,117,118,119,120,121,122,123 I & C device checking complete.Continue

  • DTW- 101,102,103,104,106,107,109,110  I & C Device checking work complete.
    ACTIVITY | DAILY REPORTS | DTW | Pappu | Parvez | REPORTS

    DTW- 101,102,103,104,106,107,109,110 I & C Device checking work complete.

    Posted onOctober 17, 2022October 17, 2022

    Listen to the Message DTW- 101,102,103,104,106,107,109,110 I & C Device checking work complete.Continue

  • CCTV Maintenance At DTW-105
    ACTIVITY | CCTV | DAILY REPORTS | DTW | REPORTS

    CCTV Maintenance At DTW-105

    Posted onOctober 17, 2022December 11, 2022

    2 Nos New Camera Installation . 2. new 20m utp cable install 3. connector change 4. IP Setup

    Listen to the Message CCTV Maintenance At DTW-105Continue

  • OGR booster pump F MOV limit switch adjustment complete.
    ACTIVITY | DAILY REPORTS | MOV | Pappu

    OGR booster pump F MOV limit switch adjustment complete.

    Posted onOctober 16, 2022October 16, 2022

    Problem: When the pump is stopped and normally shuts off, a fault automatically occurs in the mov.  In this case the valve is…

    Listen to the Message OGR booster pump F MOV limit switch adjustment complete.Continue

  • DTW 104 CCTV maintenance complete.
    ACTIVITY | CCTV | DAILY REPORTS | DTW | Jewel

    DTW 104 CCTV maintenance complete.

    Posted onOctober 10, 2022October 10, 2022

    Problem: 01 nos CC Camera Do not show footage in NAV.Problem found: Automatic IP has been changed in the dome Camera. Than IP…

    Listen to the Message DTW 104 CCTV maintenance complete.Continue

Page navigation

Previous PagePrevious 1 … 6 7 8 9 10 … 14 Next PageNext

Dhaka Water Supply and Sewerage Authority

+88 01797187749

Join With Us

© 2025 TEAM ICE

  • Home
  • ICE LAB
  • Product Specifications
  • Technical Papers