Optical Fiber restoration work at DTW103
In the time of Civil work the contractor’s people cuts down the fiber cable to conduct their civil work. As a result this…
OGR Booster pump (E) checking complete.
Problem: When the pump is stopped and normally shuts off, a fault automatically occurs in the MOV (4P01-E). In this case the valve…
Instrumentation of Month (September,2022)
Daily Work Plan September 2022đź — SL/NO Date PROBLEMS TYPE LOCATION REMARK 1 01.09.2022 DTW LIT Sensor installation work. COR DTW Team ICE: âś…PAPPU,…
IRP-1/2 Optical Fiber Maintenance Report
IRP-1 /2 Optical Fiber Maintenance Report August-2022 SL No. Location Pole (Nos) Comment 01 Chaira Bridge to DTW101 1 Nos Cable bundle disjoint…
Level Sensor Report 2022
Level Sensor Report October 2022 SL NO. DTW NO. STATIC LEVEL PUMPING LEVEL Type STATUS 01 101 5.8 ❎Level Sensor problem. 02…
VCB Installation & Commissioning
Installation and Commissioning of the vacuum circuit breaker is relatively simple, and it is a process that must be completed before leaving the…
DTW-118,122,220 & 205 automatic start-stop problem solved
Due to solving those problems : Modbus ground connection check. VFD frequency regulator loose connection check. SPD check . RJ-45 connector check. Cable…
IRP-1 & 2 all DTW CCTV UPS maintenance, replace & install
Savar-Keraniganj Well Field Plant IRP-1 & 2 all DTW’s CCTV UPS maintenance , replace & install SL No. DTW No. Problem Activity Comment…