DTW-120 PIT maintenance Done.
Rearrange cable waring. fuse change.now PIT is ok and give proper value in scada
LIT Do Not Down in The Boring After 7 Meter









DTW-120 PIT maintenance Done.
Rearrange cable waring. fuse change.now PIT is ok and give proper value in scada
LIT Do Not Down in The Boring After 7 Meter









Previous control cable is damaged by ant .so we replace new control cable
Finding: MOV 2V07-L opening & closing time percentage isn’t showing properly in SCADA & Field side. Action Taken: Reset the MOV-2V07.
Savar-Keraniganj Well Field Plant IRP-1 & 2 all DTW’s CCTV UPS maintenance , replace & install SL No. DTW No. Problem Activity Comment…
1. connector change 2. IP Setup
DTW-211 Serial Communication Cable check and Rejoin Done. Now communication normal
The Rehabilitation work is on going as long as 6 month. Any scenario of development of this DTW isn’t shown.After visiting this DTW,…