IRP-2 Sub-Station 1Nos New Server Rack Installation Done






IRP-2 Sub-Station 1Nos New Server Rack Installation Done






DTW-122 PIT Fuse and Serial communication cable check and maintenance complete.Problem: PIT value not showing in the SCADA.Problem found: 1. PIT 24v DC…
Observation: DTW 201 Radio Communication checking complete. This DTWs communication is very bad.1. In DTW 201, We checked up to 10 minutes. In…
Radio Communication problem solve and there are graphical problem in SCADA DTW 107 radio comm. checking complete.গত ৩১/১০/২০২২ তারিখ বিকাল 06:18 pm এর…
Google Map Location Lat/Long: 23°44’21.0″N 90°24’29.3″E Date: 2022.12.20 Observation: Recommendation: Pictures: Date: 2022.12.22 Date: 2022.12.24 Date: 2022.12.26
1.5Nos new camera installation 2.1Nos New PoE Switch Installation 3.1Nos New Onu Installation 4.CCTV Server Panel Installation 5.Optical Fiver Connectivity