IRP#01 Main substation, Electrical Panel Room, OGR Electrical Panel Room Cleaning & Visual Check Work Completed.



IRP#01 Main substation, Electrical Panel Room, OGR Electrical Panel Room Cleaning & Visual Check Work Completed.



Problem: This MOV is abnormal working. MOV Open time & close time 0% to 100% value not showing. IRP-2 3V07A MOV Reset, reprogramming…
Checking and maintenance of 2 field pumps completed.
FXA1PU-M56 Specifications SL NO Parameter Description 01 Brand Rextron Model FXA1PU-56L (Transmitter) FXA1PU-56R (Receiver) 02 MAX. Resolution 4096×2160@60Hz ( 4:4:4 )3840×2160@60Hz ( 4:4:4…
Problem: Do not show footage in NAV.Problem found: POE Switch problem & 1 nos cc camera damage found and New POE Switch installing. Now problem…
Fiber Optical Maintenance Near DTW-103
1.1 Nos New PoE Swich Installation . 2.Cable connector change 3. 5 Nos Camera IP Setup