ACTIVITY | DAILY REPORTS | Jewel | Pappu | Parvez | Pending Issue IRP-1 to IRP-2 SCADA controlling communication antenna Arrangement work complete. Posted onSeptember 29, 2022October 12, 2022
ACTIVITY | Parvez PWID106: IRP-1 All FCP & LOP panel clean. Posted onNovember 21, 2023November 21, 2023
ACTIVITY | DAILY REPORTS | DTW | Pappu | REPORTS IRP-2 RTU & VFD Panel Cleaning Posted onNovember 12, 2022November 12, 2022 IRP-2 RTU Panel, Server Panel & VFD Panel Cleaning Done
ACTIVITY PWID44:DTW222 Bullet camera glass and cage cleaning. Posted onNovember 16, 2023November 16, 2023
ACTIVITY DTW-211,212,213,214,215 RTU and CCTV panel Cleaning Posted onDecember 4, 2023December 4, 2023
ACTIVITY PROSOSED SYSTEM FOR CONTRACTOR WORK ENVIRONMENT Posted onSeptember 14, 2022September 14, 2022