DTW-103 VFD Controller Install
ACTIVITY | DTW | DTW103 | Parvez

DTW-103 VFD Controller Install

Posted onNovember 3, 2022November 3, 2022

1.DTW-103 New VFD Controller Install 2. Parameter set 3.Serial Communication Cable Wiring Work Done

Listen to the Message DTW-103 VFD Controller InstallContinue

DTW-106 CCTV Base Placement
ACTIVITY | CCTV | DTW

DTW-106 CCTV Base Placement

Posted onNovember 3, 2022November 3, 2022

DTW-106 CCTV Base Placement Done

Listen to the Message DTW-106 CCTV Base PlacementContinue

DAILY REPORTS | REPORTS

MOV REPORT 2022

Posted onNovember 3, 2022December 11, 2022

MOV Report 2022 November IRP1 SL NO MOV ID Status Remarks 1 2V03A ✅OK 2 2V03B ✅OK 3 2V03C ✅OK 4 2V03D ✅OK…

Listen to the Message MOV REPORT 2022Continue

ACTIVITY | DTW

DTW-107 Radio Communication Problem

Posted onNovember 2, 2022November 2, 2022

DTW-107 Radio Communication Problem Check

Listen to the Message DTW-107 Radio Communication ProblemContinue

DTW- 123 CCTV Maintenance
ACTIVITY | CCTV | DTW

DTW- 123 CCTV Maintenance

Posted onNovember 2, 2022November 2, 2022

Listen to the Message DTW- 123 CCTV MaintenanceContinue

DTW-202 CCTV Maintenance
ACTIVITY | CCTV | DTW

DTW-202 CCTV Maintenance

Posted onNovember 2, 2022November 2, 2022

1.one new camera installation 2. Connector Change 3.IP Setup

Listen to the Message DTW-202 CCTV MaintenanceContinue

DTW – 111 LIT Maintenance Work Complete.
ACTIVITY | DAILY REPORTS | DTW | Pappu

DTW – 111 LIT Maintenance Work Complete.

Posted onNovember 1, 2022November 1, 2022

Dtw 111 LIT Reinstallation complete . DTW 111 থেকে পুরাতন একটি LIT স্টোরে জমা দেয়া হয়েছে ৷

Listen to the Message DTW – 111 LIT Maintenance Work Complete.Continue

LOCAL PIPE LINE e-PRV & MOV MODIFICATION WORK.
ACTIVITY | DTW | Jewel | Pappu

LOCAL PIPE LINE e-PRV & MOV MODIFICATION WORK.

Posted onOctober 29, 2022October 29, 2022

Listen to the Message LOCAL PIPE LINE e-PRV & MOV MODIFICATION WORK.Continue

Uncategorized

MONTHLY PREVENTIVE MAINTENANC SCHEDULE NOVEMBER-2022 (Parvez)

Posted onOctober 29, 2022October 29, 2022

SL NO. DATE SCHEDULE COMMENTS 01 As per schedule IRP-1 OGR ALL I&C RELATED DEVICES CLEANING. 02 As per schedule IRP-1 SCADA ROOM…

Listen to the Message MONTHLY PREVENTIVE MAINTENANC SCHEDULE NOVEMBER-2022 (Parvez)Continue

DTW | MONTHLY REPORTS | Parvez | REPORTS

LIT & PIT report October-2022

Posted onOctober 29, 2022October 29, 2022

DTW NO. LIT PIT Comments DTW NO. LIT PIT Comments 101 NOT OK OK 201 OK OK 102 OK OK 202 NOT OK…

Listen to the Message LIT & PIT report October-2022Continue

Page navigation

Previous PagePrevious 1 … 24 25 26 27 28 … 59 Next PageNext

Dhaka Water Supply and Sewerage Authority

+88 01797187749

Join With Us

© 2025 TEAM ICE

  • Home
  • ICE LAB
  • Product Specifications
  • Technical Papers