Skip to content
TEAM ICE
  • Home
  • ICE LAB
  • Product Specifications
  • Technical Papers
TEAM ICE
  • ACTIVITY | Pappu

    FIT-3001 Maintenance

    Posted onJuly 5, 2022July 26, 2022

    After visited to IRP2, we saw that lots of water inside the chamber and the condition of the flow meter flow detector is…

    Listen to the Message FIT-3001 MaintenanceContinue

  • REPORTS

    Report: IRP-2 Dome Camera and Panel preventive maintenance.

    Posted onJuly 5, 2022July 5, 2022

    Equipment Status Dome Camera: All Ok Power Supply: Ok Ring Switch: Ok Findings: After raining water found in panel. Suggestion: Solution for water…

    Listen to the Message Report: IRP-2 Dome Camera and Panel preventive maintenance.Continue

  • REPORTS

    Report: IRP-1 Electrical Room RTU Panel Preventive Maintenance.

    Posted onJuly 5, 2022July 5, 2022

    Cleaning Status: Completed. Findings: No problem found.

    Listen to the Message Report: IRP-1 Electrical Room RTU Panel Preventive Maintenance.Continue

  • REPORTS

    Report: IRP-1 OGR Electrical Room RTU Panel Preventive Maintenance.

    Posted onJuly 5, 2022July 5, 2022

    Cleaning Status: Completed. Findings: No problem found.

    Listen to the Message Report: IRP-1 OGR Electrical Room RTU Panel Preventive Maintenance.Continue

  • REPORTS

    Report: IRP-2 Sub-station CCTV Server Panel Preventive Maintenance.

    Posted onJuly 5, 2022July 5, 2022

    Device Status OLT : OK UPS: OK ONU: Ok POE Switch : OK Findings: Too much dust inside all device. Suggestion: New separate…

    Listen to the Message Report: IRP-2 Sub-station CCTV Server Panel Preventive Maintenance.Continue

  • ACTIVITY | Parvez

    IRP-1 All DTW NEV Voltage check

    Posted onJuly 5, 2022July 26, 2022

    Listen to the Message IRP-1 All DTW NEV Voltage checkContinue

  • REPORTS

    IRP-1 DTW (101 to123) SCADAPACK, TRIO JR,LIT & PIT REPORT.

    Posted onJuly 5, 2022July 5, 2022

    DTW SCADAPACK TRIO JR LIT PIT COMMENTS 101 OK OK OK OK 102 OK OK NOT OK OK 103 OK OK OK OK…

    Listen to the Message IRP-1 DTW (101 to123) SCADAPACK, TRIO JR,LIT & PIT REPORT.Continue

  • Uncategorized

    Report: IRP-1 all DTW CCTV Panel equipment inspection and preventive maintenance. ( June-July,2022 )

    Posted onJuly 5, 2022July 5, 2022

    SL No. DTW No Cleaning POE Switch ONU UPS 01. 101 Completed OK OK Problem 02. 102 Completed OK OK Problem 03. 103…

    Listen to the Message Report: IRP-1 all DTW CCTV Panel equipment inspection and preventive maintenance. ( June-July,2022 )Continue

  • APP FOR 2022-23
    Uncategorized

    APP FOR 2022-23

    Posted onJuly 5, 2022July 24, 2022

    APP for Fiscal Year 2022-23 সাভার কেরানীগঞ্জ ওয়েল ফিল্ড প্ল্যান্ট, ঢাকা ওয়াসার অত্যন্ত গুরুতপূর্ন ও মডেল পানি শোধনাগার। প্ল্যান্টটি সম্পুর্ন অটোমেটেড এবং স্ক্যাডা…

    Listen to the Message APP FOR 2022-23Continue

  • Uncategorized

    IRP-1 DTW (101 to123) VFD & VFD CONTROLLER REPORT.

    Posted onJuly 5, 2022July 5, 2022

    DTW VFD VFD CONTROLLER COMMENTS 101 OK OK 102 OK OK 103 OK NOT OK 104 OK OK 105 OK OK 106 OK…

    Listen to the Message IRP-1 DTW (101 to123) VFD & VFD CONTROLLER REPORT.Continue

Page navigation

Previous PagePrevious 1 … 51 52 53 54 55 … 60 Next PageNext

Dhaka Water Supply and Sewerage Authority

+88 01797187749

Join With Us

© 2025 TEAM ICE

  • Home
  • ICE LAB
  • Product Specifications
  • Technical Papers