ACTIVITY PWID14:DTW114 Bullet camera glass and cage cleaning. Posted onNovember 16, 2023November 16, 2023
ACTIVITY | DAILY REPORTS | Jewel | Pappu | Parvez 4 nos Monitoring Well Level Sensor Installation Complete. Posted onSeptember 21, 2022September 21, 2022 1 :MW03B 2: MW14A 3:MW08A 4: MW13B
ACTIVITY | DAILY REPORTS | Pappu | REPORTS IRP-2 ALL LOP Panel Cleaning Posted onNovember 20, 2022November 20, 2022 There was so much dust
ACTIVITY PWID56,DTW120,121,122, 123 RTU & CCTV Panel Clening Posted onDecember 2, 2023December 2, 2023
ACTIVITY | DAILY REPORTS | Jewel | Pappu | Parvez | Pending Issue IRP-1 to IRP-2 SCADA controlling communication antenna Arrangement work complete. Posted onSeptember 29, 2022October 12, 2022
ACTIVITY | CCTV CCTV Maintenance At DTW-119 Posted onOctober 19, 2022December 11, 2022 1.1 Nos New Camera Installation . 2. connector change 3. IP Setup