- 2 Nos New Camera Installation . 2. new 20m utp cable install 3. connector change 4. IP Setup



DTW-211 Serial Communication Cable check and Rejoin Done. Now communication normal
The Rehabilitation work is on going as long as 6 month. Any scenario of development of this DTW isn’t shown.After visiting this DTW,…
26.11.2023 Today SEL manpower change the e-PRV CRD spring. And we check the e-PRV functionality is okay or not okay. MOV-1 50% Open,…
CCTV modification work for Dual power source Done Now CCTV continuous View remain All time.
DTW#217,216,209 VFD RTU AND CCTV PANEL CLEANING COMPLETE There was so much dust
DTW-113 Scada Pack Programing And Install Done