Installation and Commissioning of the vacuum circuit breaker is relatively simple, and it is a process that must be completed before leaving the…
DTW NO. LIT PIT Comments DTW NO. LIT PIT Comments 101 NOT OK OK 201 OK OK 102 OK OK 202 NOT OK…
Issue Forward to the electrical team.
1.DTW-114 1Nos Camera Install Done 2.New UTP Cable Install 3.Connector Change Now DTW-114 5Nos Camera in Operation
1.UTP Cable Change 2.Connector Change 3.IP Setup