Similar Posts

ACTIVITY | DAILY REPORTS | DTW | Pappu
DTW – 111 LIT Maintenance Work Complete.
Posted on
Dtw 111 LIT Reinstallation complete . DTW 111 থেকে পুরাতন একটি LIT স্টোরে জমা দেয়া হয়েছে ৷

ACTIVITY | DAILY REPORTS | Jewel | Pappu | Parvez
4 nos Monitoring Well Level Sensor Installation Complete.
Posted on
1 :MW03B 2: MW14A 3:MW08A 4: MW13B
WID563: IRP-2 Inside 4 Nos 360 degree camera maintenance.
Posted on
Findings: SFP problem found in 1 Nos S-Ring switch. As a result, 172.16.100.110,111,113,115 I/P assigned camera’s view isn’t shown in SCADA monitor. Action…
IRP-1 DTW (101 to123) SCADAPACK, TRIO JR,LIT & PIT REPORT.
Posted on
DTW SCADAPACK TRIO JR LIT PIT COMMENTS 101 OK OK OK OK 102 OK OK NOT OK OK 103 OK OK OK OK…
DTW201 Mass Cleaning
Posted on