Switch Gear Panel Arrangement Drawing Handover to Mr. Pappu(Assistant Shift Operator) and Mr. Parvez(Automation Technician) today (30.05.2022) at 1.43PM.
SL NO. DATE SCHEDULE COMMENTS 01 As per schedule IRP-1 OGR ALL I&C RELATED DEVICES CLEANING. 02 As per schedule IRP-1 SCADA ROOM…
Findings: Flote Switch mis-displacement problem found. Need to dressing the cable with cable tie.
Findings: Switch problem found. Action taken: Switch replace.