WID616: DTW-107 LIT, PIT, FIT isolation due to regeneration work.
Posted on
Due to regeneration work, We disconnect the connection of LIT, PIT, FIT.

IRP-1 OGR Electrical Room RTU Panel Preventive Maintenance.
Posted on
RTU Panel cleaning completed.

Team ICE Work Scope
Posted on
Preventive Work Scope SL. NO Work Name Interval Comments Estimated Date 1 SANDFILTER BED ALL LIT SENSOR CLEANING. 2 VFD…
WID558: DTW123 ELD installation and Leakage current check.
Posted on
Findings : ELD fuse burns when main UPS take input power. Action taken: 1. UPS replace but problem isn’t solved. 2. ELD replace…
WID594: Dtw-203 Radio communication error. Need to check.
Posted on
Findings: SCADAPack STAT-LED blinking in Red signal. Action Taken: Restart the SCADAPack & radio modem.