Similar Posts

Monthly Work Plan ( Jun-July )for Pappu Dhar
Posted on
Work List (Preventive Maintenance)

IRP-1 OGR Electrical Room RTU Panel Preventive Maintenance.
Posted on
RTU Panel cleaning completed.

Optical Fiber recheck for DTW-122 To 123
Posted on
Still Fiber Loss
WID558: DTW123 ELD installation and Leakage current check.
Posted on
Findings : ELD fuse burns when main UPS take input power. Action taken: 1. UPS replace but problem isn’t solved. 2. ELD replace…