Unused LIT Collect from DTW- 221,207,120,123 Done







Unused LIT Collect from DTW- 221,207,120,123 Done







1.DTW-103 New VFD Controller Install 2. Parameter set 3.Serial Communication Cable Wiring Work Done
Flexible pipe lay down,LIT Cable Enter intu Flexible pipe from Boring to RTU
when we install new VFD controller , the HMI Graph do not change from scada that time . so we reinstall old VFD…
DHAKA WASA TEAM ICE জীবনের ঝুকি নিয়ে ICE Team এভাবেই কাজ করে যাচ্ছে।
1.1Nos New Camera Installation 2. UTP Cable Change 3. Connector Change 4. IP setup