Findings: UVR being under voltage, it need a reset to execute Close Command.
Action: ACB open/close command relay check. Isolate the physical reset cable from MC.






Findings: UVR being under voltage, it need a reset to execute Close Command.
Action: ACB open/close command relay check. Isolate the physical reset cable from MC.






Modbus Serial communication cable check Complete. No problem Found in the Field LIT Do Not Down in The Boring After 10 Meter
Problem: SCADA always showing HI signal. Problem found: 1 Nos float switch problem. HI signal float switch problem & float switch connection terminal…
Optical fibber connection, CCTV PoE Switch Onu Inter connection, 5 NOS camera add in Nav-4,
DTW-102 Scada Pack Programing And Install Done
There was so much dust