1. connector change 2. IP Setup




1. connector change 2. IP Setup
Modbus Serial communication cable check Complete. No problem Found in the Field LIT Do Not Down in The Boring After 10 Meter
1 :MW03B 2: MW14A 3:MW08A 4: MW13B
ONU connection Problem . Now DTW-223 5 Nos CCTV operation in NAV-4
Due to solving those problems : Modbus ground connection check. VFD frequency regulator loose connection check. SPD check . RJ-45 connector check. Cable…
Fiber Optical Maintenance Near DTW-103