ACTIVITY Field Pump Checking & Maintenance. Posted onDecember 3, 2023December 3, 2023 Checking and maintenance of 2 field pumps completed.
ACTIVITY | DAILY REPORTS | DTW | Pappu | Parvez | REPORTS IRP-1 and IRP-2 Sludge Drying Bed LOP Control Cable Change Posted onNovember 20, 2022November 20, 2022 Previous control cable is damaged by ant .so we replace new control cable
ACTIVITY | DAILY REPORTS | DTW | Jewel | Pappu | Parvez DTW115 SCADA PACK INSTALL COMPLETE Posted onSeptember 8, 2022September 9, 2022
ACTIVITY PWID14:DTW114 Bullet camera glass and cage cleaning. Posted onNovember 16, 2023November 16, 2023
CCTV | Parvez | REPORTS IRP-2 Sub-station optical fiber arrangement done. Posted onNovember 23, 2023November 23, 2023
ACTIVITY | DAILY REPORTS | DTW | Pappu | Parvez | REPORTS DTW- 101,102,103,104,106,107,109,110 I & C Device checking work complete. Posted onOctober 17, 2022October 17, 2022