Flexible pipe lay down,LIT Cable Enter intu Flexible pipe from Boring to RTU
Similar Posts
IRP-1 DTW RTU,VFD & CCTV Panel Cleaning
Posted on
Dtw 101,102,103,109,110 RTU panel , VFD internal site & CCTV panel cleaning complete .
ACTIVITY | DAILY REPORTS | Jewel | Pappu | Parvez
OGR booster pump D winding temperature & Bearing temperature sensor checking.
Posted on
Problem: In those sensors, high temperature shows in transmitter display. But when we check the mA current of sensor signal, that was OK….
DTW-109 Radio communication check by new Antenna installing
Posted on
Due to facing lots of obstacles in front of line of sight, the radio signal is too much worst
ACTIVITY | DAILY REPORTS | Jewel | Pappu | Parvez
IRP-1 sand filter “E” ultrasonic level transmitter installing.
Posted on
New parameter setting on an old ultrasonic level transmitter and installing complete. now sand filter “E” is normal. SCADA value & field value…
DTW-115 VFD fault problem maintenance.
Posted on
VFD modbus interrupt problem found. Than reset the VFD.