1.1Nos New Camera Installation 2. UTP Cable Change 3. Connector Change 4. IP setup




1.1Nos New Camera Installation 2. UTP Cable Change 3. Connector Change 4. IP setup
Checking and maintenance of 2 field pumps completed.
PIT Status October 2022 SL NO. DTW Field Value SCADA Value Remarks 01 101 2.6.kg ✅ OK 02 102 2.1.kg ✅ OK 03…
Problem found: POE Switch & 4 NOS CC camera problem found.