CCTV PANEL, UPS, POE SWITCH, ONU CLEANING COMPLETE DTW-208 .

Posted onSeptember 6, 2022September 6, 2022

Listen to the Message CCTV PANEL, UPS, POE SWITCH, ONU CLEANING COMPLETE DTW-208 .Continue

DTW-208 RTU PANEL, VFD CLEANING & CHECKING COMPLETE.
ACTIVITY | DTW | MONTHLY REPORTS | Pappu

DTW-208 RTU PANEL, VFD CLEANING & CHECKING COMPLETE.

Posted onSeptember 6, 2022September 6, 2022

Listen to the Message DTW-208 RTU PANEL, VFD CLEANING & CHECKING COMPLETE.Continue

ACTIVITY | CCTV | DTW | Jewel | MONTHLY REPORTS

CCTV PANEL, UPS, POE SWITCH, ONU CLEANING COMPLETE DTW-203 .

Posted onSeptember 5, 2022September 6, 2022

Listen to the Message CCTV PANEL, UPS, POE SWITCH, ONU CLEANING COMPLETE DTW-203 .Continue

ACTIVITY | DTW | MONTHLY REPORTS | Pappu

DTW-203 RTU, VFD CLEANING & CHECKING COMPLETE.

Posted onSeptember 5, 2022September 6, 2022

Listen to the Message DTW-203 RTU, VFD CLEANING & CHECKING COMPLETE.Continue

Instrumentation of Month (September,2022)
ACTIVITY | DAILY REPORTS | DTW | Jewel | Pappu | Parvez

Instrumentation of Month (September,2022)

Posted onSeptember 4, 2022October 17, 2022

Daily Work Plan September 2022đź — SL/NO Date PROBLEMS TYPE LOCATION REMARK 1 01.09.2022 DTW LIT Sensor installation work. COR DTW Team ICE: âś…PAPPU,…

Listen to the Message Instrumentation of Month (September,2022)Continue

IRP-1/2 Optical Fiber Maintenance Report
ACTIVITY | CCTV | Jewel | NETWORK CONNECTIVITY | Pappu | Parvez

IRP-1/2 Optical Fiber Maintenance Report

Posted onAugust 30, 2022September 5, 2022

IRP-1 /2 Optical Fiber Maintenance Report August-2022 SL No.  Location  Pole (Nos) Comment 01 Chaira Bridge to DTW101 1 Nos Cable bundle disjoint…

Listen to the Message IRP-1/2 Optical Fiber Maintenance ReportContinue

ACTIVITY | DTW | Parvez

Level Sensor Report 2022

Posted onAugust 30, 2022November 14, 2022

Level Sensor Report October 2022 SL NO. DTW NO. STATIC LEVEL PUMPING LEVEL Type STATUS 01 101   5.8 ❎Level Sensor problem. 02…

Listen to the Message Level Sensor Report 2022Continue

ACTIVITY | DAILY REPORTS | Pappu

DTW210 to DTW213 Optical Fiber Maintenance Work

Posted onAugust 25, 2022August 25, 2022

Listen to the Message DTW210 to DTW213 Optical Fiber Maintenance WorkContinue

ACTIVITY | DAILY REPORTS

DTW201 Mass Cleaning

Posted onAugust 22, 2022August 25, 2022

Listen to the Message DTW201 Mass CleaningContinue

VCB Installation & Commissioning
ACTIVITY | Parvez | Technical Papers

VCB Installation & Commissioning

Posted onJuly 31, 2022August 24, 2022

Installation and Commissioning of the vacuum circuit breaker is relatively simple, and it is a process that must be completed before leaving the…

Listen to the Message VCB Installation & CommissioningContinue

Page navigation

Previous PagePrevious 1 … 23 24 25 26 Next PageNext

Dhaka Water Supply and Sewerage Authority

+88 01797187749

Join With Us

© 2025 TEAM ICE

  • Home
  • ICE LAB
  • Product Specifications
  • Technical Papers