  • ACTIVITY | DAILY REPORTS | Parvez | REPORTS

    IRP-1 All sandfilter ultrasonic sensor cleaning

    Posted onNovember 29, 2022November 29, 2022

    IRP-1 All sandfilter ultrasonic sensor cleaning Done. There was so much dust

    Listen to the Message IRP-1 All sandfilter ultrasonic sensor cleaningContinue

  • ACTIVITY | DAILY REPORTS | Parvez | REPORTS

    IRP-1 All Doom Camera Lens & Camera Panel Cleaning

    Posted onNovember 29, 2022November 29, 2022

    IRP-1 360° Dome camera lens cleaning done. All panel brush to reduce dust. There was so much dust

    Listen to the Message IRP-1 All Doom Camera Lens & Camera Panel CleaningContinue

  • DTW#217,216,209 VFD RTU AND CCTV PANEL CLEANING
    ACTIVITY | DAILY REPORTS | DTW | Jewel | Pappu | REPORTS

    DTW#217,216,209 VFD RTU AND CCTV PANEL CLEANING

    Posted onNovember 29, 2022November 29, 2022

    DTW#217,216,209 VFD RTU AND CCTV PANEL CLEANING COMPLETE There was so much dust

    Listen to the Message DTW#217,216,209 VFD RTU AND CCTV PANEL CLEANINGContinue

  • DTW #120,121,122 VFD , RTU AND CCTV PANEL CLEANING
    ACTIVITY | DAILY REPORTS | DTW | Jewel | Parvez | REPORTS

    DTW #120,121,122 VFD , RTU AND CCTV PANEL CLEANING

    Posted onNovember 27, 2022November 27, 2022

    DTW #120,121,122 VFD , RTU AND CCTV PANEL CLEANING COMPLETE

    Listen to the Message DTW #120,121,122 VFD , RTU AND CCTV PANEL CLEANINGContinue

  • IRP-2 All FCP panel cleaning
    ACTIVITY | DAILY REPORTS | DTW | Jewel | Pappu | REPORTS

    IRP-2 All FCP panel cleaning

    Posted onNovember 24, 2022November 26, 2022

    IRP 2 FCP ক্লিনিং কাজ সম্পন্য হয়

    Listen to the Message IRP-2 All FCP panel cleaningContinue

  • IRP-2 Sub-Station CC Camera Maintenance
    ACTIVITY | CCTV | DAILY REPORTS | DTW | Parvez

    IRP-2 Sub-Station CC Camera Maintenance

    Posted onNovember 24, 2022November 24, 2022

    IRP- 2 1nos CC Camera Maintenance done, there was connector problem. now IRP-2 Sub-Station all CC Camera in operation.

    Listen to the Message IRP-2 Sub-Station CC Camera MaintenanceContinue

  • DTW-122 & 123 Optical Fiber Maintenance
    ACTIVITY | CCTV | DAILY REPORTS | DTW | Parvez

    DTW-122 & 123 Optical Fiber Maintenance

    Posted onNovember 24, 2022November 24, 2022

    DTW-122,123 optical fiber maintenance: We check TJ box in both dtw. Optical fiber checked by Leaser Light. Leaser light throw from dtw-122 to…

    Listen to the Message DTW-122 & 123 Optical Fiber MaintenanceContinue

  • ACTIVITY | DAILY REPORTS | DTW | Jewel | Pappu | REPORTS

    DTW-221,217,123 VFD Controller And Serial Communication Check

    Posted onNovember 23, 2022November 23, 2022

    DTW-221,217,123 Modbus communication Problem DTW-221 & 217 new serial communication cable install DTW- 123 VFD controller and Modbus serial communication cable check Done….

    Listen to the Message DTW-221,217,123 VFD Controller And Serial Communication CheckContinue

  • Optical Fiber Maintenance
    ACTIVITY | CCTV | DAILY REPORTS | DTW | Jewel | NETWORK CONNECTIVITY | Pappu | Parvez | REPORTS

    Optical Fiber Maintenance

    Posted onNovember 21, 2022November 22, 2022

    Optical Fiber Maintenance For DTW- 114,115,117,118,119,120,121,122,123 The Optical Fiber Cable is Burn By REB Cable short Circuit, That’s why we change New 611…

    Listen to the Message Optical Fiber MaintenanceContinue

  • IRP-2 ALL LOP Panel Cleaning
    ACTIVITY | DAILY REPORTS | Pappu | REPORTS

    IRP-2 ALL LOP Panel Cleaning

    Posted onNovember 20, 2022November 20, 2022

    There was so much dust

    Listen to the Message IRP-2 ALL LOP Panel CleaningContinue

Page navigation

Previous PagePrevious 1 2 3 4 5 6 … 14 Next PageNext

Dhaka Water Supply and Sewerage Authority

+88 01797187749

Join With Us

© 2025 TEAM ICE

  • Home
  • ICE LAB
  • Product Specifications
  • Technical Papers