Daily Work Plan September 2022🠗 SL/NO Date PROBLEMS TYPE LOCATION REMARK 1 01.09.2022 DTW LIT Sensor installation work. COR DTW Team ICE: ✅PAPPU,…
DTW#217,216,209 VFD RTU AND CCTV PANEL CLEANING COMPLETE There was so much dust
Checking and maintenance of 2 field pumps completed.
In DTW-109, there are 4 Nos maintenance and installation : 1 Nos new PoE switch install. 2. 3 Nos new camera install. 3….
IRP-1 Sand Filter FCP Panel Cleaning Done
Problem: OGR Booster pump E running time Moter current high (682 Amp) showing than pump stop that time frequency is 0.3 Hz (Abnormal).Problem…