Findings: Lots of hanging TJ box is visiable.
Action Taken: Reduce TJ box replacing optical fiber.










Findings: Lots of hanging TJ box is visiable.
Action Taken: Reduce TJ box replacing optical fiber.










Radio Communication problem solve and there are graphical problem in SCADA DTW 107 radio comm. checking complete.গত ৩১/১০/২০২২ তারিখ বিকাল 06:18 pm এর…
The Rehabilitation work is on going as long as 6 month. Any scenario of development of this DTW isn’t shown.After visiting this DTW,…
Daily Work Plan October 2022🠗 SL/NO Date PROBLEMS TYPE LOCATION REMARK 1 01.10.2022 DTW-105 CCTV checking maintenance. COR CCTV Team ICE: ✅PAPPU, Parvez,…
2 Nos New Camera Installation . 2. new 20m utp cable install 3. connector change 4. IP Setup
106,117,118 এবং 223 এই DTW গুলো তে আগে পাওয়ার চলে গেলে ফল্ট ধরে রাখত যার কারণে অপরেশন টিম থেকে লোক পাঠিয়ে এটা রিসেট…
DTW-122 PIT Fuse and Serial communication cable check and maintenance complete.Problem: PIT value not showing in the SCADA.Problem found: 1. PIT 24v DC…