  • A new PoE switch install at DTW-201
    ACTIVITY | CCTV | DTW | Pappu | Parvez

    A new PoE switch install at DTW-201

    Posted onOctober 6, 2022October 6, 2022

    Previous PoE switch has port problem.

    Listen to the Message A new PoE switch install at DTW-201Continue

  • REPORTS

    CCTV Footage Analysis Data

    Posted onOctober 4, 2022October 8, 2022

    DTW107 Missing Footage Time SL No Date Tme /= Duration Reason 1 2022.08.20 12 AM – 8.05 AM = 8 Hours 5 Minute…

    Listen to the Message CCTV Footage Analysis DataContinue

  • Instrumentation Findings of Month (October,2022)
    ACTIVITY | DAILY REPORTS | Jewel | Pappu | Parvez

    Instrumentation Findings of Month (October,2022)

    Posted onOctober 4, 2022October 24, 2022

    Daily Work Plan October 2022🠗 SL/NO Date PROBLEMS TYPE LOCATION REMARK 1 01.10.2022 DTW-105 CCTV checking maintenance. COR CCTV Team ICE: ✅PAPPU, Parvez,…

    Listen to the Message Instrumentation Findings of Month (October,2022)Continue

  • DTW#201 CCTV Checking Maintenance Complete.
    ACTIVITY | CCTV | DAILY REPORTS | DTW | Jewel | Pappu | Parvez

    DTW#201 CCTV Checking Maintenance Complete.

    Posted onOctober 2, 2022October 2, 2022

    Problem: Do not show footage in NAV.Problem found: POE Switch problem & 1 nos cc camera damage found and New POE Switch installing. Now problem…

    Listen to the Message DTW#201 CCTV Checking Maintenance Complete.Continue

  • DTW#105 CCTV Checking Maintenance Complete.
    ACTIVITY | CCTV | DAILY REPORTS | DTW | Jewel | Pappu | Parvez

    DTW#105 CCTV Checking Maintenance Complete.

    Posted onOctober 2, 2022October 2, 2022

    Problem: Do not show footage in NAV.Problem found: Optical Network Unit (ONU) problem & 2 nos cc camera damage found and New ONU installing. Now…

    Listen to the Message DTW#105 CCTV Checking Maintenance Complete.Continue

  • IRP-1 sand filter “E” ultrasonic level transmitter installing.
    ACTIVITY | DAILY REPORTS | Jewel | Pappu | Parvez

    IRP-1 sand filter “E” ultrasonic level transmitter installing.

    Posted onSeptember 29, 2022September 29, 2022

    New parameter setting on an old ultrasonic level transmitter and installing complete. now sand filter “E” is normal. SCADA value & field value…

    Listen to the Message IRP-1 sand filter “E” ultrasonic level transmitter installing.Continue

  • IRP-1 to IRP-2 SCADA controlling communication antenna Arrangement work complete.
    ACTIVITY | DAILY REPORTS | Jewel | Pappu | Parvez | Pending Issue

    IRP-1 to IRP-2 SCADA controlling communication antenna Arrangement work complete.

    Posted onSeptember 29, 2022October 12, 2022

    Listen to the Message IRP-1 to IRP-2 SCADA controlling communication antenna Arrangement work complete.Continue

  • New parameter setting on an old ultrasonic level transmitter.
    ACTIVITY | DAILY REPORTS | Jewel | Pappu | Parvez

    New parameter setting on an old ultrasonic level transmitter.

    Posted onSeptember 28, 2022September 28, 2022

    Listen to the Message New parameter setting on an old ultrasonic level transmitter.Continue

  • Dtw-122 serial Comm.New UTP Cable installing complete.
    ACTIVITY | DAILY REPORTS | DTW | Pappu | Parvez

    Dtw-122 serial Comm.New UTP Cable installing complete.

    Posted onSeptember 28, 2022September 28, 2022

    Problem: : Modbus com interrupt problem.Problem found:The serial communication cable was cut by rat 🐁. then UTP Cable installing . new pump is…

    Listen to the Message Dtw-122 serial Comm.New UTP Cable installing complete.Continue

  • DTW#106,117,118 AND 223 PTT AND UVR CHECKING COMPLETE
    ACTIVITY | DAILY REPORTS | DTW | Jewel | Pappu | Parvez

    DTW#106,117,118 AND 223 PTT AND UVR CHECKING COMPLETE

    Posted onSeptember 28, 2022September 28, 2022

    106,117,118 āĻāĻŦāĻ‚ 223 āĻāχ DTW āϗ⧁āϞ⧋ āϤ⧇ āφāϗ⧇ āĻĒāĻžāĻ“āϝāĻŧāĻžāϰ āϚāϞ⧇ āϗ⧇āϞ⧇ āĻĢāĻ˛ā§āϟ āϧāϰ⧇ āϰāĻžāĻ–āϤ āϝāĻžāϰ āĻ•āĻžāϰāϪ⧇ āĻ…āĻĒāϰ⧇āĻļāύ āϟāĻŋāĻŽ āĻĨ⧇āϕ⧇ āϞ⧋āĻ• āĻĒāĻžāĻ āĻŋāϝāĻŧ⧇ āĻāϟāĻž āϰāĻŋāϏ⧇āϟ…

    Listen to the Message DTW#106,117,118 AND 223 PTT AND UVR CHECKING COMPLETEContinue

Page navigation

Previous PagePrevious 1 … 12 13 14 15 16 … 20 Next PageNext

Dhaka Water Supply and Sewerage Authority

+88 01797187749

Join With Us

© 2026 TEAM ICE

  • Home
  • ICE LAB
  • Product Specifications
  • Technical Papers