Findings: UVR being under voltage, it need a reset to execute Close Command.
Action: ACB open/close command relay check. Isolate the physical reset cable from MC.






Findings: UVR being under voltage, it need a reset to execute Close Command.
Action: ACB open/close command relay check. Isolate the physical reset cable from MC.
Dtw 111 LIT Reinstallation complete . DTW 111 থেকে পুরাতন একটি LIT স্টোরে জমা দেয়া হয়েছে ৷
DTW-120 PIT maintenance Done. Rearrange cable waring. fuse change.now PIT is ok and give proper value in scada LIT Do Not Down in…
1.one new camera installation 2. Connector Change 3.IP Setup