1. IP Setup


1. IP Setup


Due to facing lots of obstacles in front of line of sight, the radio signal is too much worst
CCTV modification work for Dual power source Done Now CCTV continuous View remain All time.
VFD Report November 2022 SL NO. DTW NO. Controller Status VFD Status Serial Communication Remarks 01 101 OK OK ✅OK 02 102 OK…
IRP#01 Main substation, Electrical Panel Room, OGR Electrical Panel Room Cleaning & Visual Check Work Completed.
Due to solving those problems : Modbus ground connection check. VFD frequency regulator loose connection check. SPD check . RJ-45 connector check. Cable…
1.DTW-114 1Nos Camera Install Done 2.New UTP Cable Install 3.Connector Change Now DTW-114 5Nos Camera in Operation