ACTIVITY | DAILY REPORTS | Jewel | Pappu | Parvez4 nos Monitoring Well Level Sensor Installation Complete.
Posted on1 :MW03B 2: MW14A 3:MW08A 4: MW13B
ACTIVITY | DAILY REPORTS | Parvez | REPORTSBreaker installation for SCADA control Room Monitor.
Posted onBreaker installation for SCADA control Room Monitor Done
ACTIVITY | DAILY REPORTS | DTW | Jewel | ParvezPIT maintenance work report (IRP-2)
Posted onPIT maintenance work reportDtw-213 maintenance. Now okDtw-208 maintenanceNow okDtw-207 maintenanceNow okDtw-211 PIT damagedDtw-203 PIT doesn’t exist.Dtw-205 PIT damagedDtw-206 SCADA PACK doesn’t exist
- ACTIVITY | DTW | Parvez | Uncategorized
WID585:Dtw-117 e-PRV CRD isn’t functioning properly. SEL manpower need to check.Now e-PRV CRD & flowmeter works
Posted on26.11.2023 Today SEL manpower change the e-PRV CRD spring. And we check the e-PRV functionality is okay or not okay. MOV-1 50% Open,…
IRP-1 & 2 all DTW CCTV UPS maintenance, replace & install
Posted onSavar-Keraniganj Well Field Plant IRP-1 & 2 all DTW’s CCTV UPS maintenance , replace & install SL No. DTW No. Problem Activity Comment…
ACTIVITY | CCTV | DAILY REPORTS | DTW | ParvezIRP-2 Sub-Station CC Camera Maintenance
Posted onIRP- 2 1nos CC Camera Maintenance done, there was connector problem. now IRP-2 Sub-Station all CC Camera in operation.