Breaker installation for SCADA control Room Monitor Done





Breaker installation for SCADA control Room Monitor Done





PIT Interlock
Cleaning Status: Completed. Findings: No problem found.
Modbus Serial communication cable check Complete. No problem Found in the Field LIT Do Not Down in The Boring After 10 Meter
New UPS installed at DTW-218 and old UPS brought to plant for problem checking. Now the pump is running and everything is normal.