জীবনের ঝুকি নিয়ে ICE Team এভাবেই কাজ করে যাচ্ছে।


























IRP- 2 1nos CC Camera Maintenance done, there was connector problem. now IRP-2 Sub-Station all CC Camera in operation.
Breaker installation for SCADA control Room Monitor Done
DTW-102 Scada Pack Programing And Install Done
DTW-120 PIT maintenance Done. Rearrange cable waring. fuse change.now PIT is ok and give proper value in scada LIT Do Not Down in…
1.5Nos new camera installation 2.1Nos New PoE Switch Installation 3.1Nos New Onu Installation 4.CCTV Server Panel Installation 5.Optical Fiver Connectivity