IRP-2 Server Rack Installation and Optical Fiber Rejoin Done

















IRP-2 Server Rack Installation and Optical Fiber Rejoin Done

















Unable to take LIT, due to keep heavy machinery in DTW compound. We collect Electronic PIT, Manual Pressure Gauge. And disconnect power supply…
Findings: Lots of hanging TJ box is visiable. Action Taken: Reduce TJ box replacing optical fiber.
Problem: after power up time ACB do not close from the SCADA command.Problem found: 27X M/C Magnetic Contact & AUX CONTACT UNIT Problem…
Table of Contents DTW SCADA PANEL ROOM OGR ELECTRICAL PANEL ROOM SAND FILTER ELECTRICAL PANEL ROOM DOME CAMERA PANEL DTW SL NO Item…
Due to facing lots of obstacles in front of line of sight, the radio signal is too much worst