Device Status
OLT : OK
UPS: OK
ONU: Ok
POE Switch : OK
Findings: Too much dust inside all device.
Suggestion: New separate panel Installation for OLT device.
Device Status
OLT : OK
UPS: OK
ONU: Ok
POE Switch : OK
Findings: Too much dust inside all device.
Suggestion: New separate panel Installation for OLT device.
1 :MW03B 2: MW14A 3:MW08A 4: MW13B
1.CCTV Pool Installation 2.CCTV Camera Cage Installation 3.UTP Cable Installation
IRP-1 360° Dome camera lens cleaning done. All panel brush to reduce dust. There was so much dust
Problem: Do not show footage in NAV.Problem found: ONU & 1 Nos cc camera Problem found.
Savar-Keraniganj Well Field Plant IRP-1 & 2 all DTW’s CCTV UPS maintenance , replace & install SL No. DTW No. Problem Activity Comment…
Problem: SCADA always showing HI signal. Problem found: 1 Nos float switch problem. HI signal float switch problem & float switch connection terminal…