ACTIVITY | DAILY REPORTS | DTW | REPORTS DTW-202 NEW LIT INSTALLATION Posted onNovember 14, 2022November 14, 2022 There was a damaged LIT. After regeneration work we have install a new LIT
ACTIVITY | DAILY REPORTS DTW210 to DTW213 Optical Fiber Maintenance Work Posted onAugust 25, 2022August 25, 2022
ACTIVITY | DAILY REPORTS | DTW | REPORTS DTW#217,216,209 VFD RTU AND CCTV PANEL CLEANING Posted onNovember 29, 2022November 29, 2022 DTW#217,216,209 VFD RTU AND CCTV PANEL CLEANING COMPLETE There was so much dust
ACTIVITY | DAILY REPORTS | DTW | REPORTS DTW- 101,102,103,104,106,107,109,110 I & C Device checking work complete. Posted onOctober 17, 2022October 17, 2022
ACTIVITY | DAILY REPORTS | DTW EPRV work with DTW 103 by ICE Team & SEL Posted onOctober 22, 2022October 22, 2022
ACTIVITY | CCTV | DAILY REPORTS | REPORTS Office Building CCTV Install Posted onDecember 9, 2022December 9, 2022 IRP-1 Office Building 1 Nos New Camera Install For Security Purpose