Daily Work Plan September 2022🠗 SL/NO Date PROBLEMS TYPE LOCATION REMARK 1 01.09.2022 DTW LIT Sensor installation work. COR DTW Team ICE: ✅PAPPU,…
1.1 NOS new Camera installing 2.UTP Cable Change 3. Connector Chang
The modbus serial communication cable is cut by mouse. The cable reconnect & solve the problem.
IRP-2 RTU Panel, Server Panel & VFD Panel Cleaning Done
Due to solving those problems : Modbus ground connection check. VFD frequency regulator loose connection check. SPD check . RJ-45 connector check. Cable…