ACTIVITY | DAILY REPORTS | DTW | REPORTS Unused LIT Collect from DTW- 221,207,120,123 Posted onDecember 3, 2022December 3, 2022 Unused LIT Collect from DTW- 221,207,120,123 Done
ACTIVITY | DAILY REPORTS | REPORTS Breaker installation for SCADA control Room Monitor. Posted onDecember 1, 2022December 1, 2022 Breaker installation for SCADA control Room Monitor Done
ACTIVITY | DAILY REPORTS | DTW | REPORTS IRP-1 (101 to 123) & IRP-2 (201 to 223) I & C device checking complete. Posted onOctober 22, 2022October 22, 2022
ACTIVITY | DAILY REPORTS | DTW | REPORTS IRP-2 RTU & VFD Panel Cleaning Posted onNovember 12, 2022November 12, 2022 IRP-2 RTU Panel, Server Panel & VFD Panel Cleaning Done
ACTIVITY | CCTV | DTW CCTV Maintenance At DTW-120 Posted onOctober 27, 2022October 27, 2022 Connector change IP Setting
ACTIVITY PWID43:DTW221 Bullet camera glass and cage cleaning. Posted onNovember 16, 2023November 16, 2023