Findings: UVR being under voltage, it need a reset to execute Close Command.
Action: ACB open/close command relay check. Isolate the physical reset cable from MC.






Findings: UVR being under voltage, it need a reset to execute Close Command.
Action: ACB open/close command relay check. Isolate the physical reset cable from MC.






Problem: In those sensors, high temperature shows in transmitter display. But when we check the mA current of sensor signal, that was OK….
DTW-106 CCTV Base Placement Done
IRP-1. CC Camera Server Panel Cleaning Done
when we install new VFD controller , the HMI Graph do not change from scada that time . so we reinstall old VFD…